Project Summary | |
---|---|
Project Name: | Adco's Bab Integrated Facilities Expansion Project |
Facility Type: | Oil / Gas production |
Client: | Abu Dhabi Company for Onshore Oil Operations .Adco. |
Budget (US $): | 1,750,000,000 |
Project Initiation: | Not Given |
Project Completion:: | Dec 09, 2019 |
Status: | PMC Awarded,EPC Awarded, |
Location: | Bab |
Project Current Status |
---|
Adnoc has awarded a $30mn contract to provide detailed engineering services for a period of three years to Bilfinger Tebodin Middle East for its onshore North East Bab project. North East Bab is part of the Bab field, which has a production capacity of almost 450,000 bpd. (November 2022) |
Project History |
---|
|
Project Contract Awards - Feed | ||
---|---|---|
Contractor Prequalified | Contractor Bids Submitted | Contractor Awarded | Contract Value |
|
|
|
Project Contract Awards - PMC | ||
---|---|---|
Contractor Prequalified | Contractor Bids Submitted | Contractor Awarded | Contract Value |
|
|
|
Project Contract Awards - EPC | ||
---|---|---|
Contractor Prequalified | Contractor Bids Submitted | Contractor Awarded | Contract Value |
|
|
|
Related Projects |
---|
No Related Projects |
Project Schedule |
---|
October 2014: Invitation to Bid for EPC December 2015: EPC Tender Cancelled January 2017: Invitation to bid for revised EPC tender March 2017: Bids submitted for revised EPC tender July 2017: Commercial bids submitted for revised EPC tender September 2017: ITB for revised commercial offers September 2017: Revised commercial bids submitted November 2017: Contract Awarded EPC April 2019: EPC technical bids submitted for Integrated Facilities Expansion 2019: Expected start-up and commissionin |
Project Scope |
---|
The project scope involves the expansion of the Bab Integrated Facilities to develop the emirate's Bab field, located southwest of Abu Dhabi.
The project will raise Adco's overall oil production from 1.4 million bpd to 1.8 million bpd.
Surface facilities will be delivered for the Thamama-A, Thamama-H and Thamama-B production zones to achieve a total sustainable oil production rate of 450 million bpd.
The integrated facilities expansion will include a new well fluid gathering system comprising off-plot wells, well bays, flowlines, manifolds and other associated hardware and equipment.
It also includes an additional processing train with a 176,000-barrel-per-day total liquids capacity in the existing Bab Central Degassing Station (BCDS) with associated facilities.
In addition, the successful contractor will also be responsible for the modifications to the existing BCDS facilities.
Bab Far North is part of the Bab field, which has a production capacity of almost 450,000 bpd. The project marks another step towards boosting oil production capacity to 5 million bpd by 2030, up from the existing 4 million bpd capacity. |
Project Structure: |
The project client is Abu Dhabi Company for Onshore Oil Operations (Adco). Adco is majority-owned by Adnoc, which has a 60% stake in the state-owned onshore giant. BP and France’s Total each hold a 10% interest. Japan’s Inpex has a 5% interest in Adco and South Korea’s GS Energy has 3%. In addition, the remaining 12% stake in Adco was recently taken up by two Chinese companies. China’s state-controlled China National Petroleum Corporation was awarded an 8% stake by Adco, while the remaining 4 % was taken by CEFC China Energy. |
AbdulM Al Kindi | |
---|---|
Address: | Abu Dhabi Company for Onshore Oil Operations .Adco., Abu Dhabi, United Arab Emirates |
Designation: | General Manager |
Department: | ADCO - Projects |
Phone: | +971 2 604 3622 |
Fax: | +971 2 666 6360 |
Abu Dhabi Company for Onshore Oil Operations UAE | |
---|---|
Address: | P.O. Box 270, Abu Dhabi, United Arab Emirates |
Phone: | +9712-6040000 |
Fax: | +9712-6665523 |
AhmedAl Hammadi | |
---|---|
Address: | Abu Dhabi Company for Onshore Oil Operations .Adco., Abu Dhabi, United Arab Emirates |
Designation: | Business Manager |
Department: | ADCO - Project Field Services |
Phone: | +971 2 604 4900 |
Fax: | +971 2 604 4759 |
ArefAl Sayed | |
---|---|
Address: | P.O. Box 270 Abu Dhabi, U.A.E. |
Designation: | Procurement Manager |
Department: | ADCO |
Phone: | +97126043715 |
Fax: | +97126650848 |