Project Summary | |
---|---|
Project Name: | Bahrain EWA’s Al Dur Independent Water and Power Project (IWPP) – Phase II |
Facility Type: | IWPP - Independent Water and Power Project |
Client: | Bahrain’s Electricity & Water Authority (EWA) |
Budget (US $): | 1,000,000,000 |
Project Initiation: | Not Given |
Project Completion:: | Jun 07, 2022 |
Status: | PMC Awarded,EPC Awarded, |
Location: | Ad Dur |
Project Current Status |
---|
HRH Prince Salman bin Hamad Al Khalifa, Bahrain's Crown Prince and Prime Minister, has inaugurated on May 30 the Al Dur 2 Phase Two IWPP. The key facility is the first production station in the kingdom connected to the high-voltage electricity transmission network of 400 KV. The station was established by Bahrain's Electricity and Water Authority (EWA) in partnership with Acwa Power. The IWPP generates 1,500 MW of electricity and processes 50 million gallons of desalinated water daily. This takes the kingdom’s overall production capacity to 5,044 MW of electricity and 204 million gallons of desalinated water daily. (June 2023) |
Project History |
---|
|
Project Contract Awards - Feed | ||
---|---|---|
Contractor Prequalified | Contractor Bids Submitted | Contractor Awarded | Contract Value |
|
|
|
Project Contract Awards - PMC | ||
---|---|---|
Contractor Prequalified | Contractor Bids Submitted | Contractor Awarded | Contract Value |
|
|
|
Project Contract Awards - EPC | ||
---|---|---|
Contractor Prequalified | Contractor Bids Submitted | Contractor Awarded | Contract Value |
|
|
|
Related Projects |
---|
No Related Projects |
Project Schedule |
---|
August 2015: Invitation to Bid for PMC June 2016: Bid submission PMC November 2016: Contract Award PMC August 2017: Pre-qualification documents submitted for BOO contract November 2017: Bid Submission for PMC of Water Transmission Project January 2018: Invitation to Bid for EPC August 2018: Bid Submission EPC November 2020: Contract Award for EPC of Water Transmission Project Q2 2022: Expected Commissioning & start-up |
Project Scope |
---|
The project scope involves the development of the planned phase II of Al Dur Independent Water and Power Project (IWPP) in Bahrain.
The project aims to more than double the plant’s existing power generation capacity of 1200 MW by adding a further 1500 MW. It will have a desalination component of about 50 million imperial gallons a day (MIGD).
EWA will purchase the power under a 20-year power purchase agreement (PPA).
KPMG Fakhro of Netherlands is the financial adviser for the project. The Trowers & Hamlins of UK is legal adviser and WSP of Canada appointed as technical adviser for the project.
The project is part of EWA’s strategy to meet future demand for electricity, which is expected to grow by an average of up to 6.4 percent until 2020. |
Project Structure: |
The project is owned, operated and managed by Bahrain’s Electricity & Water Authority (EWA). |
RashidAl Kaabi | |
---|---|
Address: | Ministry of Electricity & Water, P.O. Box 2, Manama, Bahrain, Arabian Gulf. |
Designation: | H.E The Minister's Office Manager |
Department: | Executive Management |
Phone: | .+973. 17522030 |
Fax: | .+973. 17552016 |
Salman Abdul RasoolKhalaf | |
---|---|
Address: | Ministry of Electricity & Water P.O. Box 2, Manama, Bahrain |
Designation: | - |
Department: | Executive Management |
Phone: | .+973. 522080 |
Fax: | .+973. 522039 |