NHPC anticipates three units of 250 MW each of the Subansiri Lower hydro project at Gerukamukh, Arunachal Pradesh to be completed by May 2025. The remaining five units of 250 MW each will be completed by May 2026 in a phased manner.
The company noted that in the context to the flash flood which occurred in October 2023 at the Teesta-V power station in Sikkim, wherein the amount of damage to the tune of Rs 1,075.97 crore has been reported to the insurer.
All the major restoration work (Civil & HM) packages, 1 to 5 have been awarded and restoration activities are ongoing.