Raysut Cement Signs Agreement to Upgrade Clinker Cooler Line 3 at Salalah

Raysut Cement Company (RCC), Oman’s largest cement manufacturer, has signed an agreement with Ayoki Engineering for the upgradation of the company’s clinker cooler line 3 at Salalah in the sultanate's Dhofar province.

 

As an EPC (engineering, procurement and construction) contractor, Ayoki will source all the equipment for the clinker cooler upgrade from IKN, Germany, said a statement from Raysut.

 

Under the agreement with Ayoki, the existing grate cooler at its Salalah plant will be replaced by IKN Pendulum clinker cooler designed for 4,000 tonnes per day (tpd) with a guaranteed capacity of 3,500 tpd clinker production, it added.

 

On the deal, group CEO Joey Ghose said: "The upgrade of clinker cooler is in line with Raysut’s strategic plan to install the latest in production technology to reduce costs as well as to scale up its plants with state-of-the art equipment."

 

"The project's scope includes civil works, supply and installation works of mechanical and electrical works related the clinker cooler upgrade. Sourcing and installation of the refractory will also be under the responsibility of EPC contractor through IKN," stated Ghose.

 

Final installation of the project will be planned during fourth quarter of 2019 and is scheduled for 35 days flame off - flame on, he added.