CEPCO Completes Testing of 525 kV HVDC Underground Cable Circuits

CEPCO (Civil and Electrical Projects Contracting) has completed specialized high-voltage direct current (HVDC) underground cable field testing on three cable circuits in Abu Dhabi, UAE, marking what the company describes as the first post-installation HVDC cable field testing of its kind in the Middle East.

The testing works involved newly installed 525 kV HVDC underground cable circuits, including cables supplied by Sumitomo Electric of Japan and Prysmian, as well as the integration of a new cable circuit into an existing HVDC cable system.

The assignment demonstrates CEPCO’s capabilities in specialized high-voltage testing, cable commissioning support and the handling of complex technical requirements associated with long-distance HVDC transmission infrastructure.

CEPCO’s scope of work covered the transportation of high-voltage DC testing equipment, on-site assembly and handling, high-voltage testing, and controlled cable discharging operations following the completion of each test.

The company deployed testing equipment rated at 800 kV DC and 35 kVA to perform the high-voltage tests and subsequent discharging operations.

Testing Case 1: Two New 525 kV HVDC Cable Circuits

On 20 May 2026, CEPCO carried out high-voltage field testing on two new 525 kV HVDC cable circuits supplied by Sumitomo Electric of Japan. Each circuit was associated with a Dedicated Metallic Return (DMR) cable.

The reported cable length was approximately 140,000 metres per circuit. The tests were conducted at a voltage of -580 kV DC for one hour, followed by a 48-hour discharge period.

Testing Case 2: New HVDC Cable Circuit Integrated with an Existing System

On 6 August 2026, CEPCO conducted high-voltage testing on a new HVDC cable circuit connected to an existing HVDC cable system, with both the new and existing cables supplied and installed by Prysmian.

The new cable section measured approximately 132,000 metres, while the existing cable section measured approximately 132,000 metres, bringing the combined length of the looped cable system to approximately 264,000 metres.

The test was performed at -464 kV DC for one hour, followed by a 48-hour discharge period. The lower test voltage, compared with the first case, reflected the consideration given to the existing cable circuit, which was already in service.

HVDC underground cable systems require specialized testing procedures because their insulation behaves differently under direct current (DC) stress compared with high-voltage alternating current (HVAC) systems.

Although cross-linked polyethylene (XLPE) is used as insulation in both technologies, HVDC insulation is particularly sensitive to space-charge accumulation, electrical conductivity variations, temperature gradients and residual cross-linking by-products. These factors must be considered when assessing cable integrity and performance under sustained DC voltage.

The testing of HVDC circuits also requires carefully controlled charging and discharging procedures, particularly for long cable sections. The 48-hour discharge periods reported for both testing cases reflect the extended discharge requirements associated with these installations.

Dedicated Metallic Return cables are an important component of certain HVDC transmission systems. They provide an alternative path for return current under specified operating conditions, helping support system continuity when the primary return path is unavailable, subject to the system design and operating arrangements.