GAIL to Complete Srikakulam-Angul Pipeline Project in June, 2026

GAIL (India) Limited has announced a revision in the completion schedule for its Srikakulam-Angul Pipeline Project. The total pipeline length is 744 km, comprising 422 km of the main line and 322 km of spur line.

While the main line was successfully commissioned on September 26, 2025, the spur line faced delays due to pending forest clearance for a 56 km section. The necessary permissions were progressively received by June 23, 2025, with tree cutting permissions granted up to September 2025. Currently, tree cutting work is in progress, and the revised project completion is now scheduled for June 2026.

The revision was approved by GAIL’s Board of Directors in their meeting held on January 3, 2026. The company confirmed that the disclosure is in compliance with SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015.